MRWA – Tonkin Gap Project (Soft Landscaping)

Project name

MRWA Tonkin Gap Project (Soft Landscaping)

Client or sector

Tonkin Gap Alliance (MRWA, BMD, Georgiou, Public Transport Authority, WA Limestone, BG&E, GHD)

Location

Bayswater, WA 6053

Project type

Revegetation, Environmental Rehabilitation, Soft Landscaping

What was delivered

  • Installation of 220,000x Native Greenstock (50mm) across Road & Rail Reserves
  • Installation of 50x 35L Trees
  • 3 Year Environmental Monitoring & Maintenance Period

Project duration

Stage 1 Construction: March 2022 – September 2023

Stage 1 Maintenance Period: September 2023 – September 2026

Stage 2 Construction: March 2024 – September 2024

Stage 2 Maintenance Period: September 2024 – September 2027